A. "SUPPLY AND TRIAL OPERATION OF THE SLUDGE DEWATERING UNIT FOR THE KALYVES WWTP" B. "SUPPLY AND INSTALLATION OF SUPPLEMENTARY TREATMENT UNITS AND TRIAL OPERATION OF THE WASTEWATER TREATMENT PLANT FOR THE KALYVES SETTLEMENT"

AWARD AUTHORITY

Municipality of Apokoronas

CONTRACTOR

THALIS E.S. S.A.

REGEON

Region of Crete

PROGRESS

98%

The supply includes:

  • The construction of a pre-thickening tank with an active volume of 40 m³.
  • A sludge dewatering unit within a 40” container, where all the required equipment will be installed.
  • The unit will be equipped with an odor control system.
  • Dismantling of equipment, demolition of concrete structures, and restoration of the geometry and watertightness of existing tanks.
  • A compact biological treatment unit with ultrafiltration membranes (MBR) providing a flow rate of 200 m³/day. The unit consists of three self-supporting prefabricated treatment tanks and a housing structure where the service equipment will be installed. The housing structure will be constructed from metal elements and polyurethane panels.
  • Infrastructure works and networks.
  • A 12-month trial operation period.

  • Two enclosed pre-treatment units, each with a capacity of 45 m³/h. Each unit includes screening, sand removal, and grease removal. The unit will be equipped with an odor control system.
  • In the existing biological reactor, two new additional horizontal surface aerators, four flow guides, and one submersible centrifugal pump for the removal of excess sludge will be installed.